Payment notice calculator

Enter a payment due date and get the notice deadlines that follow from it under the Construction Act.

The statutory default: the payment notice is due not later than 5 days after the payment due date; the final date for payment is 17 days after the due date under the Scheme; and a pay less notice must be given not later than 7 days before the final date for payment. Christmas Day, Good Friday and bank holidays don’t count towards those periods.

This is a general guide to the statutory default position under the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts, using England & Wales bank holidays. Your contract may set different periods and different rules for serving notices, and it takes priority. This is not legal advice. If a date matters, check it with us.

Payment notices: common questions

When must a payment notice be given?

Under the Construction Act, the payer must give a payment notice not later than five days after the payment due date, stating the sum it considers due and the basis on which it is calculated. If the contract sets a shorter period, the contract applies.

When must a pay less notice be given?

A pay less notice must be given no later than the period the contract specifies before the final date for payment. Where the contract is silent, the Scheme for Construction Contracts applies a period of seven days before the final date for payment.

How are the days counted?

Section 116 of the Construction Act says the period starts immediately after the specified date, and that Christmas Day, Good Friday and bank holidays are disregarded. Weekends are counted as normal days.

What happens if no payment notice is given?

If the payer does not give a valid payment notice, the payee may be able to rely on its own application or a default payment notice, and the sum in it becomes the notified sum. That sum must be paid by the final date for payment unless a valid pay less notice is given.

Does the Construction Act apply to every construction contract?

It applies to most construction contracts in the UK, but not to contracts with residential occupiers and not to certain excluded operations. Some contracts also fall outside the statutory definition of construction operations.