In short: A final account is the contract sum adjusted for everything that changed: variations, provisional sums, dayworks, claims for time and money, contra charges and retention. Accounts get agreed when each element is priced against the contract mechanism and supported by contemporaneous records. They stall when they are submitted as a total with no route back to the contract.
Final accounts rarely stall because the parties are far apart on principle. They stall because the submission cannot be checked: a large number, a poor narrative, and no way for the person on the other side to determine entitlement under the contract.
What a final account contains
Whatever the form of contract, the account is the contract sum adjusted for what actually happened:
- the contract sum, and any agreed adjustments to it;
- variations or compensation events, valued under the contract’s own rules;
- provisional sums, expended and adjusted;
- dayworks, where properly instructed and recorded;
- fluctuations, if the contract provides for them;
- extension of time, and the associated loss and expense or compensation for delay;
- contra charges and set-off claimed by the other side;
- retention, and the dates for its release;
- credits and omissions, which are as much a part of the account as the additions.
Start before the job ends
Almost everything that decides the outcome happens earlier:
- variations instructed and priced as they arise, not valued a year later;
- notices given at the time, in the form the contract requires;
- delay recorded against a programme that was current;
- records kept in a form the receiving party can follow and understand: allocation sheets, site instructions, correspondence, photographs, labour returns.
An account assembled from contemporaneous records as the project progresses is stronger, allowing a true valuation exercise to be undertaken.
Structure the submission so it can be checked
Give the reviewer a route from the contract to the submission:
- Summary: contract sum, each adjustment, and the total, on one page.
- Element by element: each variation with its instruction, its valuation rule and its build-up.
- Time: the delay narrative, the analysis, and the entitlement claimed.
- Money linked to time: loss and expense tied to the periods, with the basis of each head clearly stated.
- The other side’s position: contra charges addressed head-on rather than ignored.
- Appendices: the evidence, indexed and referenced from the build-ups.
If a reviewer has to ask for a document to check any number, the account has a gap.
Price what is likely, not what is hoped for
Every account contains items that are strong, arguable and weak. Presenting all three at the same confidence damages the strong ones. Mark the position honestly, internally at least, and lead with what is evidenced.
The same discipline applies to the CVR: if the account claims more than the reporting ever recognised, somebody will ask why.
Watch the contractual mechanism at the end
Both JCT and NEC route the final payment through defined steps with defined dates, and amendments often change them. Two things to check before you do anything else:
- the deadline for submitting the account after practical completion or the defects certificate;
- the effect of a failure to respond by the other party, which in some forms turns silence into agreement.
The payment notice rules still apply to the final payment. They are missed just as often at the end of a job as in the middle of it.
Then negotiate
Once the account is checkable, negotiation is about value rather than about documents. Go in knowing your acceptable position, the items you will be willing to deal on, and the ones you will take to adjudication if you have to, and make sure the account you submitted supports that position.